ARMY TM 5-5420-212-23
MARINE CORPS TM 08676A-23/3
Section II. DIRECT SUPPORT MAINTENANCE PROCEDURES
CAUTION
MGB primary components are highly stressed and early detection of crack damage is most
Important. Delay in detection of cracks may result In complete failure of a component.
NOTE
During inspections, pay particular attention to all welds, top and bottom chords of highly
stressed components and all connectors and lugs.
TASK
PROCEDURE
PAGE NO.
3-2
Pallet Adapter
3-6
3-3
Push Bar Adapter, Brackets
3-10
3-4
Panel Erection Aid
3-12
3-5
Push Bars Short, Long, End Fittings
3-16
3-7
Roller Beam, Plain Roller Assembly
3-25
3-6
Roller Beam, Flanged Roller Assembly
3-25
3-8
Launching Nose Cross Girder, Roller Assembly
3-27
3-9
Hydraulic Jack 15T
3-29
3-10
Hydraulic Jack 20T
3-42
3-11
Landing Roller
3-56
3-12
Launching Nose Roller, Roller Assembly
3-58
3-13
Rocking Roller, Overhaul
3-60
3-5